University of Sussex

Client: University of Sussex
Contract value: £1,100,000
Contract period: 30 weeks

Shawcross and Richmond Lecture Theatres

The project consisted of stripping out of the three lecture theatres and removing all fixed seating to storage.  Removing all floor coverings, suspended ceilings, all existing M&E services to include all existing air conditioning and ductwork.

Design and install new structural steel support framework and reinforced concrete bases to facilitate installing three new separate air conditioning systems to provide heating and cooling into the individual lecture theatres.

As part of the refurbishment works – installation of new lighting systems, suspended ceilings, automated blackout blinds, redecorations and new floor coverings and re-installing all lecture theatre seating on completion.